City Waste Water Modernization Project

A small city in Oregon has a major water reclamation modernization program.

Client

Small Oregon City

Completion time

4 weeks of planning, 2 weeks of work

Services

Excavation and Grading, Custom Services Scope for Infrastructure Demolition and Removal, Hauling, and Recycling

Share on

Our project

We are proud of our work and would like to share our project

This town approved a multi-phase program to modernize how they deal with wastewater.

The storage facility was inadequate and to prepare for a new treatment plant, a new water tower was required. The BANR team participated early in city planning, identified key partners, built the team and engaged once all local approvals completed. First was brush clearing and tree removal to get the heavy equipment in - delivered by train. Next demolition of the old tower including removal for recycling. Last we prepared a new site for the new wastewater treatment plant storage tank.